Scheduled Schuylkill County Road Work - Week Ending 01/26/18
----------------------------------------------
Municipality: Blythe Twp.
ROAD NAME: Burma Road
BETWEEN: Morea Road AND St. Clair
Type of Work: Brush Cutting
Work being Done By: PENNDOT Maintenance Forces
Type of Restriction: Daytime
RESTRICTION: Lane restriction with flagging.
START DATE: 01/22/2018 Est. Completion Date: 01/26/2018
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays? YES
----------------------------------------------
Municipality: Pine Grove Twp
ROAD NAME: Interstate 81
BETWEEN: Lebanon County Line AND Exit 100 (Pine Grove)
Type of Work: Other
Work being Done By: PENNDOT Maintenance Forces
Type of Restriction: Daytime
RESTRICTION: Lane restriction in both directions.
START DATE: 01/22/2018 Est. Completion Date: 01/25/2018
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
----------------------------------------------
Municipality: Kline / Delano Twp.
ROAD NAME: Lofty Road
BETWEEN: PA 309 AND Delano Road
Type of Work: Drainage
Work being Done By: PENNDOT Maintenance Forces
Type of Restriction: Daytime
RESTRICTION: Lane restriction with flagging.
START DATE: 01/16/2018 Est. Completion Date: 01/20/2018
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays? NO
----------------------------------------------
Municipality: West Penn Twp.
ROAD NAME: PA 309
BETWEEN: Tamaqua Borough AND Snyders
Type of Work: Pothole Patching
Work being Done By: PENNDOT Maintenance Forces
Type of Restriction: Daytime
RESTRICTION: Lane restriction with flagging.
START DATE: 01/22/2018 Est. Completion Date: 01/26/2018
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays? NO
----------------------------------------------
Municipality: Delano
ROAD NAME: Tamanend Road
BETWEEN: Fairview Street AND Hazel Street
Type of Work: Brush Cutting
Work being Done By: PENNDOT Maintenance Forces
Type of Restriction: Daytime
RESTRICTION: Lane restriction with flagging.
START DATE: 01/16/2018 Est. Completion Date: 01/20/2018
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays? NO
----------------------------------------------
Municipality: Butler/New Castle Twp.
ROAD NAME: Interstate 81
BETWEEN: Exit 119 (Highridge Park Road) AND Exit 124 (PA 61)
Type of Work: Crack Sealing
Work being Done By: PENNDOT Maintenance Forces
Type of Restriction: Daytime
RESTRICTION: Lane restriction both directions.
START DATE: 01/22/2018 Est. Completion Date: 01/25/2018
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays? NO
----------------------------------------------
Municipality: Pine Grove Township
ROAD NAME: Interstate 81
BETWEEN: Exit 100 (PA 443) AND Lebanon County Line
Type of Work: Inspection
Work being Done By: PENNDOT Bridge Inspection Forces
Type of Restriction: Daytime
RESTRICTION: Northbound Lane Restriction from 9:00AM to 12:00PM
Southbound Lane Restriction from 12:00PM to 3:00PM
START DATE: 01/23/2018 Est. Completion Date: 01/23/2018
Restrictions in Effect (time of day): 9:00 AM To 3:00 PM
Will Rain Cause Delays? YES
Sponsored by |