Saturday, November 3, 2018

Upcoming Schuylkill County Road Work


Upcoming Schuylkill County Road Work from PennDOT


------------------------------------

Municipality:  Delano Township
Road name:  Interstate 81.
Between:  Exit 134 (Delano) and Exit 138 (PA 309)
Type of work:  Inspection
Work being done by:  PennDOT Bridge Inspection Forces
Type of restriction:  Daytime
Restriction:  Northbound lane restriction.
Start date:  11/27/18
Est completion date:  11/27/18
Restrictions in effect (time of day):  09:00 AM To 03:00 PM
Will rain cause delays?  Yes
Change/Update:  INSPECTION RESCHEDULED FROM 10/23 TO 11/27/18


------------------------------------

Municipality:  Butler Twp.
Road name:  PA 54
Between:  Girardville Borough and Lost Creek
Type of work:  Drainage
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  11/5/18
Est completion date:  11/9/18
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No
Change/Update:


------------------------------------

Municipality:  Butler Twp.
Road name:  PA 61
Between:  Frackville and Ashland
Type of work:  Crack Sealing
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Northbound lane restriction.
Start date:  11/6/18
Est completion date:  11/9/18
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No
Change/Update:


------------------------------------

Municipality:  Union Twp.
Road name:  Aristis Road
Between:  Little Mountain Road and Columbia County Liine
Type of work:  Pothole Patching
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  11/5/18
Est completion date:  11/9/18
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No
Change/Update:


------------------------------------

Municipality:  New Castle Twp.
Road name:  Burma Road
Between:  Valley Road and Darkwater Road
Type of work:  Other
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  11/6/18
Est completion date:  11/9/18
Restrictions in effect (time of day):  07:00 AM To 03:00 AM
Will rain cause delays?  No
Change/Update:  Flood Repair


------------------------------------

Municipality:  Eldred
Road name:  Mountain Road
Between:  Pitman and Helfenstein
Type of work:  Pothole Patching
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  11/5/18
Est completion date:  11/9/18
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No
Change/Update:


------------------------------------

Municipality:  Various
Road name:  Interstate 81
Between:  Exit 107 (US 209) and Exit 112 (PA 25)
Type of work:  Bridge Repair
Work being done by:  PennDOT Contractor
Type of restriction:  24 Hours
Restriction:  Lane restriction northbound for bridge deck repairs.
Start date:  11/5/18
Est completion date:  11/8/18
Restrictions in effect (time of day):  06:00 AM To 12:00 PM
Will rain cause delays?  No
Change/Update:


------------------------------------

Municipality:  Various
Road name:  Interstate 81
Between:  Exit 107 (US 209) and Exit 112 (PA 25)
Type of work:  Milling & Paving
Work being done by:  PennDOT Contractor
Type of restriction:  24 Hours
Restriction:  Lane restriction 24-hour southbound for milling and paving work.
Start date:  11/7/18
Est completion date:  11/9/18
Restrictions in effect (time of day):  06:00 AM To 09:00 AM
Will rain cause delays?  No
Change/Update: