Road Work Scheduled Schuylkill County Next Week
------------------------------------
Municipality: Pine Grove Twp.
Road name: PA 443/Suedburg Road
Between: Pine Grove Borough and Suedburg
Type of work: Shoulder Work/Widening
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction.
Start date: 2/11/19
Est completion date: 2/15/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update:
------------------------------------
Municipality: Foster Twp.
Road name: Interstate 81
Between: Exit 119 (Highridge Park Road) and Exit 107 (US 209)
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction both directions.
Start date: 2/11/19
Est completion date: 2/14/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update:
------------------------------------
Municipality: Ryan Twp,
Road name: Interstate 81
Between: Exit 124 (PA 61) and Exit 131 (PA 54)
Type of work: Shoulder Work/Widening
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction both directions.
Start date: 2/11/19
Est completion date: 2/14/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update:
------------------------------------
Municipality: Butler / Mahanoy / Ryan / Rush Twps.
Road name: PA 54
Between: Ashland Borough and Hometown
Type of work: Other
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 2/11/19
Est completion date: 2/15/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update:
------------------------------------
Municipality: West Mahanoy / East Union Twps.
Road name: PA 924
Between: Shenandoah Borough and Sheppton
Type of work: Drainage
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 2/11/19
Est completion date: 2/15/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update:
------------------------------------
Municipality: West Penn Twp.
Road name: US 209
Between: Carbon County Line and Tamaqua Borough
Type of work: Pothole Patching
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 2/11/19
Est completion date: 2/15/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update:
------------------------------------
Municipality: Gilberton Boro.
Road name: PA 924
Between: Frackville Borough and Shenandoah Borough
Type of work: Bridge Repair
Work being done by: PennDOT Maintenance Forces
Type of restriction: Daytime
Restriction: Lane restriction with flagging.
Start date: 2/11/19
Est completion date: 2/15/19
Restrictions in effect (time of day): 07:00 AM To 03:00 PM
Will rain cause delays? No
Change/Update: