Saturday, March 2, 2019

ROAD WORK: PennDOT Announces Road Work Scheduled for Schuylkill County


This week's weather may impact this schedule but PennDOT has announced scheduled Schuylkill County Road Work.

------------------------------------

Municipality:  Gilberton Boro.
Road name:  PA 924
Between:  Frackville Borough and Shenandoah Borough
Type of work:  Bridge Repair
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction both directions.
Start date:  3/4/19
Est completion date:  3/8/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No


------------------------------------

Municipality:  West Mahanoy Twp.
Road name:  US 209
Between:  Carbon County Line and Tamaqua Borough
Type of work:  Pothole Patching
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  3/4/19
Est completion date:  3/8/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No


------------------------------------

Municipality:  Mahanoy / Ryan / Blythe Twps.
Road name:  Burma Road
Between:  Morea Road and SR 61
Type of work:  Brush Cutting
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  3/4/19
Est completion date:  3/8/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No


------------------------------------

Municipality:  Ryan Twp.
Road name:  Interstate 81
Between:  Exit 124 (PA 61) and Exit 131 (PA 54)
Type of work:  Shoulder Work/Widening
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction both directions.
Start date:  3/4/19
Est completion date:  3/7/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No


------------------------------------

Municipality:  Butler / Mahanoy / Ryan / Rush Twps.
Road name:  PA 54
Between:  Ashland Borough and Hometown
Type of work:  Other
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  3/4/19
Est completion date:  3/8/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No
Change/Update:  Spray Patching Potholes


------------------------------------

Municipality:  West Mahanoy / East Union Twp.
Road name:  PA  924
Between:  Shenandoah Borough and Sheppton
Type of work:  Drainage
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction with flagging.
Start date:  3/4/19
Est completion date:  3/8/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No


------------------------------------

Municipality:  Foster Twp.
Road name:  Interstate 81
Between:  Exit 119 (Highridge Park Road) and Exit 107 (US 209)
Type of work:  Pothole Patching
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction both directions.
Start date:  3/4/19
Est completion date:  3/7/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No


------------------------------------

Municipality:  Pine Grove Twp.
Road name:  PA 443
Between:  Pine Grove Borough and Suedburg
Type of work:  Shoulder Work/Widening
Work being done by:  PennDOT Maintenance Forces
Type of restriction:  Daytime
Restriction:  Lane restriction in both directions.
Start date:  3/4/19
Est completion date:  3/8/19
Restrictions in effect (time of day):  07:00 AM To 03:00 PM
Will rain cause delays?  No
Change/Update:

-------------------------------------